South Africa
Eskom announces Stage 2 load-shedding─── 05:33 Fri, 08 Nov 2019

Eskom announced on Thursday evening that it would implement Stage 2 load-shedding from 22pm until the early hours of Friday morning.
"Eskom will implement stage 2 rotational load-shedding this evening from 22:00 until 05:00 tomorrow morning," the power utility said.
It said it had lost three generators' units earlier in the day and had to use emergency reserves throughout.
"As a result our emergency reserves are now at critically low levels and need to be replenished overnight in order to meet tomorrow’s forecasted demand in electricity.
"That said, the risk of load-shedding for tomorrow remains high if generating units do not return overnight as scheduled."
Stage 2 load-shedding allows for 2,000 MW of power to be load shed on a rotational basis.