South Africa
Eskom Implements Stage 2 load-shedding─── 12:33 Mon, 10 Oct 2022
Eskom will implement stage 2 load-shedding on Monday from 4pm until Wednesday at midnight.
The rolling blackouts come in spite of generation units at Kriel and a unit each at Kendal, Komati, Lethabo, Majuba and Matla power stations returning to service on Saturday.
"The load-shedding will be used to replenish emergency generation reserves during the night to bolster generation capacity,” says Eskom spokesperson, Sikonathi Mantshantsha.
"To the extent possible, Eskom will endeavour to limit load-shedding to night-time to have minimal impact on the economy and population.”
#Stage2 #loadshedding is currently being implemented.
— Eskom Hld SOC Ltd (@Eskom_SA) October 11, 2021
Schedules can be downloaded from https://t.co/UzMtttaJ4q or accessed via #MyEskomApp
Municipal customers to check schedule with local municipalities pic.twitter.com/UU0o8xmEpK
Mantshantsha says a generating unit each at Kendal and Kusile power stations has been taken offline for repairs.